Marine

Waterfront Repairs and New Fuel System

Project Details

Marine
Pensacola, FL
Client: United States Coast Guard
Project Size: $0M – $2M

Project Description

This design-bid-build project included the repair of an existing bulkhead wall and the installation of a new fuel system.  The bulkhead wall was leaking at the joints due to high wear from tropical storms and hurricanes.  In order to repair the bulkhead wall, approximately 6,000 SF of concrete slab along the 160 LF of shoreline was removed.  The Coast Guard’s original repair design called for divers to pack the back side of the joint with oakum and dig down 15’ on the land side where forms would be placed on each joint.  Once the forms were placed, the plans called for grout to be injected from the water side of the joint by divers.  Sergent Construction (SC) attempted this method which did not work because of the high-water table found on the land side of the wall.  SC did a quick redesigned repair approach which placed a new back up wall behind the existing bulkhead wall.  Forms were then placed on the back side of the wall along with welded wire fabric for reinforcement.  The concrete was then pumped into place with most of the forms remaining under the water level.  Sergent Constructions ingenuity increased project safety and sped up the project delivery time.

Pile Replacement at USCG Base LA/LB

Project Details

Marine
San Pedro, California
Client: United States Coast Guard
Project Size: $0M – $1.5M

Project Description

The project’s scope of work involved repairs and replacements of existing piles near and around the boat basin at the United States Coast Guard’s Base LA/LB located in San Pedro, California.  Many of the existing mooring piles and creosoted fender piles at this Coast Guard Station were corroded and delipidated from the harsh coastal marine water and environment.  This presented challenging circumstances to remove the piles, sometimes done in pieces due to the degree of corrosion and disintegration.  In addition to removing some piles in pieces, other piles had to be removed by using special drilling equipment to loosen the sandstone and hard ground before removal was possible.

The replacement of the mid-basin piles was done with the drilling and driving of new Polymeric piles, filled with 5000 PSI concrete.  After installing the piles, Sergent construction applied a fiber reinforced wrap to protect the piles from corrosion, weathering, biological growth, and constant impact from the ocean.  This work was performed under the watch eye of the Marine Mammal Monitoring agency, assigned to document and ensure that the construction and renovation efforts would not interfering with sea life.