Facility Maintenance & Repair

Repair Research Aircraft Hangar B4802 HVAC System

Project Details

Facilities Maintenance, Repair, & Modernization
NASA Armstrong Flight Research Center,
Edwards, CA

Client: National Aeronautics and Space Administration Armstrong (NASA)
Project Size: $2M – $5M

Project Description

This project’s scope of work involved the renovation and rehabilitation of NASA’s Research Hangar B4802 HVAC system.  The existing HVAC system at the hangar consisted of nine direct evaporative cooling units mounted on 10’ tall structural steel frames.  The existing HVAC system in its entirety was demolished and replaced.

The new HVAC system consisted of seven 35,000 CFM and 25,0000 CFM indirect direct evaporative coolers with and without gas heat.  The AHUs were provided with factory installed and tested HVAC DDC systems to speed up project production.  Once the AHUs were set, the HVAC DDC controls were tied into the existing Siemens HVAC DDC system and the base wide energy monitoring system.  Additionally, entirely new supply and return ductwork was also installed on the exterior of the hangar to service the new AHUs.  Existing louvers and duct penetrations were blocked off to allow for the new relief air dampers to provide the proper air changes required for aircraft hangars per the UFC.

Piping Chilled Water System

Project Details

Facilities Maintenance, Repair, & Modernization
VA Medical Center, Cheyenne, WY
Client: Department of Veterans Affairs
Project Size: $2M – $5M

Project Description

This project’s scope of work involved the complete renovation and rehabilitation of the Cheyenne VA Medical Center’s central chilled water plant located in the basement of the Clinical Additions building.  The existing chilled water plant consisted of 3 chillers, 3 cooling towers, and the associated chilled water and condenser pumps.  In order to meet the needs of an ever-expanding Cheyenne VA Medical Center, the VA needed to expand the capacity of the chilled water plant from 900 to 1,200 tons of cooling.  The existing chilled water plant consisted of two existing 250-ton chiller and one new 400-ton variable speed magnetic bearing chiller that was installed by SCS on a previous chilled water plant rehabilitation project 6 month’s prior.

Work included the replacement of the two remaining 250-ton cooling towers with two new 400-ton cooling tower to meet the cooling needs of the 2 new 400-ton variable speed magnetic bearing chillers.  The existing 400-ton cooling tower installed 6 months prior by SCS was retained and reinstalled on a new structural steel frame.  Additional installed equipment included a side stream filtration system for the condenser water, 10” pipe diameter air separator, expansion tank, automated water treatment system, three new vertical 25 HP Condenser Water Pump, 50 HP base mounted Chilled Water Pump, precast 7,180-gallon condenser water cistern tank, and the relocation and reutilization of two existing 50 HP base mounted chilled water pumps, and three new vertical inline 15 HP Chilled Water Pumps.

Revitalize Mission Control Electrical Systems

Project Details

Facilities Maintenance, Repair, & Modernization
NASA Armstrong Flight Research Center,
Edwards, CA

Client: National Aeronautics and Space Administration (NASA)
Project Size: $5M – $8M

Project Description

This project’s scope of work involved the complete renovation and rehabilitation of the NASA’s Mission Control electrical system.  The removed Mission Control electrical system consisted of antiquated manual transfer switches that operated two redundant Uninterruptable Power Source (UPS) located in Bldg. 4848.  The two existing 400KW UPSs contained only 15 minutes of battery life and were insufficient to handle Mission Control’s increased electrical loads.  Additional electrical equipment removed include 3-400A Panelboards, one 600A Panelboard, two 1200A Switchgears, and all associated feeders and branch circuits.

The revitalized Mission Control electrical system consisted of new and cutting-edge critical power system equipment.  This included five new 150/300 KVA Power Distribution Units (PDU) with integrated digital building management systems or Building Automation System (BAS) controls including touchscreen graphical user interface control panels.  In addition, two new 450 KW UPS’s with 30 minutes of battery life and touch screen graphical user interface BAS controls were also installed.  These two were provided to ensure that NASA’s Mission Control had ample time to safely terminate active missions in the event of a power failure.

In order to handle the increased cooling loads of the electrical panelboards and UPSs housed in Bldg. 4848, the entire HVAC system for this portion of the building was removed and replaced.  This included all new ductwork.  Site work also included the installation of 13 free standing structural steel frames to support new above grade emergency power electrical feeders for mission controls.  The fire alarm in Bldg. 4848 was also removed, replaced, and tied into the base wide fire alarm system.  Finally, due to this project’s critical nature, an extensive engineering verification and testing of all newly installed equipment was performed.  This included a new and existing electrical system arc flash and power coordination study.

Replace HVAC, Ceiling, and Lighting, Ft Campbell HS

Project Details

Facilities Maintenance, Repair, & Modernization
Ft Campbell, KY
Client: : United States Army Corps of Engineers
Project Size: $5M – $10M

Project Description

This project involved the renovation and rehabilitation of Ft. Campbell High School’s 100,000 SF campus located in Ft. Campbell, KY.  This project’s scope included the removal and replacement of existing HVAC system, numerous ceilings, and various lighting systems.  The existing HVAC system at the school was in disrepair after 30 years of use coupled with poor maintenance.  The new HVAC system consisted of one new 365-ton chiller, an entirely new chilled water piping system, 65 fan coils units, 5 inside air handlers, new ductwork throughout, and nine roof top air handlers.  The chilled water system was comprised of redundant 30 HP chilled water pumps and 365-ton air cooled chiller all equipped with variable frequency drives for optimum efficiency.  In order to integrate the new HVAC system with portion of the old system that were not replaced, an entirely new Delta Controls HVAC DDC control system was installed in both the existing and renovated portions of the school.  The DDC control system was also linked to the base wide BACnet system allowing for centralized monitoring and control of the facility by Ft. Campbell’s public works department.

Improve Mechanical Utilities, Phase 4

Project Details

Facilities Maintenance, Repair, & Modernization
VAMC Gainesville, FL
Client: Department of Veterans Affairs
Project Size: $5M – $8M

Project Description

This project included the installation of a new 80,000 cubic feet per minute (CFM) outdoor central station air handler unit (AHU) located on the second-floor roof.  In order to support the new AHU, an entirely new structural steel platform was erected with stairs and walkways around the exterior.  Once the unit was installed, a new mechanical penthouse was constructed around the AHU to protect the AHU and associated systems from the elements.

This project also included the removal and installation of a 21,000 CFM indoor central station AHU.  Work also included installation of new single coil VAV’s, supply and return ductwork throughout the renovated area, heating hot water piping system with heat exchanger, new DDC controls, new fire alarm devices, and abatement of asbestos.

Replace AC & Environmental Controls, Phase 3

Project Details

Facilities Maintenance, Repair, & Modernization
VAMC Gainesville, FL
Client: Department of Veterans Affairs
Project Size: $2M – $5M

Project Description

This project involved the installation of one custom indoor centration station 15,000 Cubic Foot Per Minute (CFM) Air Handler Units (AHU) to service the VA hospital’s laboratory and associated administrative area.  The project also called for the installation of a 14,000 CFM rooftop AHU to service the sterile storage and Sterile Processing Department (SPD) areas of the hospital.  The facilities existing HAVC DDC and electrical systems were expanded to facilitate the addition of the equipment.  Additional rooftop work included the installation of a chilled water plant to support the new roof mounted AHU.

The chilled water plant consisted of parallel 15 HP pumps, VFDS, expansion tanks, air separator, chilled water piping, and a 150-ton air cooled chiller.  New structural steel platforms, complete with ladders and walkways, were installed to support both the new rooftop AHU and 150-ton air cooled chiller.  Also included was the installation of a steam to hot water heat exchanger system to provide hot water to the VAV

Additional Pumps and Piping for CA2

Project Details

Facilities Maintenance, Repair, & Modernization
VA Medical Center, Cheyenne, WY
Client: Department of Veterans Affairs
Project Size: $0M – $2M

Project Description

This project’s scope of work involved the renovation and rehabilitation of a portion of the Cheyenne VA Medical Center’s central chilled water plant located in the basement of the Clinical Additions Building.  The existing chilled water plant consisted of 3 chillers, 3 cooling towers, and the associated chilled water and condenser pumps.  In order to meet the needs of an ever-expanding Cheyenne VA Medical facility, this project’s scope of work included the removal of one existing 250-ton chillers and replacing it with a 400-ton variable speed magnetic bearing chiller.  Work also included the replacement of the existing 250-ton cooling tower and structural framework to support a new 400-ton cooling tower and framework to meet the cooling needs of the new 400-ton variable speed magnetic bearing chiller.

Additional installed equipment included a side stream filtration system for the condenser water, 25 HP Condenser Water Base Mounted Pump, 25 HP Chilled Water Base Mounted Pump, 2-50 HP Secondary Chilled Base Mounted Water Pumps, and 2-20 HP Water Side Heat Exchanger Base Mounted Water Pumps.  In order to make the entire chilled water plant more efficient a 522-ton plate and frame heat exchanger was installed along with variable frequency drives on the cooling tower, water pumps, and chiller.  In total, the installed chilled water capacity on this project was 922 tons when taking into consideration the capacity of both the chiller and heat exchanger.

Repair HVAC Systems, Building 20, 310, & 400

Project Details

Facilities Maintenance, Repair, & Modernization
Fort Irwin National Training Center, Fort Irwin, CA
Client: United States Army Corps of Engineers
Project Size: $0M – $2M

Project Description

This project’s scope of work involved the complete renovation and rehabilitation of the HVAC systems in Buildings 20, 310, and 400 at the Ft. Irwin National Training Center located in Ft. Irwin, CA.  Building 20 is located at the Barstow-Daggett Airport approximately 30 miles from post and is the Army’s Fire Station that services their airborne cavalry training unit.  Building 400 is Ft. Irwin’s fire station while Building 310 is the MWR’s movie theater facility.  The scope of work for each building is as follows:

  • Building 20’s scope of work included the removal and replacement of the existing chilled water system including the replacement of the chiller with a new 30 TON York Air Cooled Unit, new chilled water distribution piping (supply and return), chilled water pump, and mechanical insulation. HVAC DDC work consisted of a new HVAC DDC front end, controllers, and integration of the existing control components into the new HVAC DDC front end.
  • Building 310’s scope of work included the complete renovation of the movie theater’s HVAC system. Work included the demolition and replacement of the existing DX chiller, chiller condensing unit, central station AHUS, and rooftop package units.
  • Building 400’s scope of work included the complete renovation of the fire station HVAC system. Work included the demolition of the two existing DX split air handlers, three updraft furnaces, VAVs, and two Rooftop Evaporative Coolers.

In addition, new Heating, Ventilation and Air Conditioning (HVAC) Direct Digital Control (DDC) systems were installed in each of the 3 buildings.  The HVAC DDC work consisted of a new HVAC DDC front end, controllers, and all migration of existing control components for each building into the new HVAC DDC front end.  The new HVAC DDC front end was then tied into the existing campus wide Niagara Building Management Systems.

Remove and Replace Makeup Air Units (MAU) and Power Roof Ventilators (PRV) exhaust fans for WHSE 28

Project Details

Facilities Maintenance, Repair, & Modernization
Defense Distribution Depot San Joaquin, Tracy, CA
Client: Defense Logistics Agency
Project Size: $0M – $2M

Project Description

This project’s scope of work involved the removal and replacement of the Makeup Air Units (MAU) and Power Roof Ventilator (PRV) exhaust fans for the 160,000 SF Warehouse Number 28 located at the Defense Distribution Depot San Joaquin, Tracy, CA.  The existing HVAC system consisted of 10 rooftop evaporative coolers for supply air and ten rooftop exhaust fans for the return air.  The existing supply ductwork was deficient due to rust and degradation.

The revitalized and renovated HVAC consisted of ten new custom fabricated stainless-steel rooftop evaporative AHUs ranging in size from 8,000 CFM to 13,000 CFM and ten rooftop exhaust fans rated at 12,000 CFM.  The AHU’s were constructed of stainless steel to improve the unit’s operational life span.  Additionally, the units were equipped with hot water coils or gas heaters to allow the units to serve both the buildings cooling and heating needs.  Each unit was custom built which enabled the units to fit the existing roof curbs and supports.  In order to increase system efficiency, the AHU’s were also equipped with VFDs.  All AHU plenums and supply ductwork were removed and replaced.  In addition, a new HVAC DDC system was also installed

Repair by Replacement Chillers, B712 HVAC

Project Details

Facilities Maintenance, Repair, & Modernization
Schriever Air Force Base, CO
Client: Department of the Air Force
Project Size: $0M – $2M

Project Description

This project’s scope of work involved the removal and replacement of three 225 tons air cooled chillers at the US Air Force’s Space Command at Schriever AFB.  Additional site work included the installation of larger Cast in Place (CIP) concrete equipment pads to accommodate the larger chillers.  The new BACnet equipped chillers were tied into the existing HVAC DDC with a new HVAC Sequence of Operations, control points, and alarms.  Additional work included the installation of a temporary chiller during construction to ensure the requisite HVAC system redundancy requirements for the facility were met.

On this design-bid-build construction contract, Sergent Construction (SC) acted as general contractor as well as self-performed the following trades: demolition, mechanical, & electrical.  In total, SCS self-performed 95% of this project’s scope of work.

Reduce Heat and Power Loss - VA Medical Center

Project Details

Facilities Maintenance, Repair, & Modernization
VA Medical Center, Cheyenne, WY
Client: Department of Veterans Affairs
Project Size: $0M – $2M

Project Description

As part of the VA’s commitment to increase energy efficiency and upgrade their infrastructure, the VA Medical Center, Cheyenne, WY constructed a state-of-the-art combined heat and power plant.  This plant’s purpose was to reduce the facility’s overall efficiency by allowing the medical center to produce its own power and use the heat generated from the facility’s generators to heat the medical center.  In order to allow the facility’s plant to operate more efficiently, SCS’s contract scope of work called for the removal of one 150 HP Cleaver Brooks boiler and the installation of two new 3,000 MBH ultra high efficiency condensing boilers.  The purpose of these new condensing boilers was to augment the heat generated by the combined heat and power plant, on an as needed basis, to allow the campus’ hot water heating system to operate at the proper heating hot water loop temperature thereby optimizing system efficiency.

Replace Air Handling Units, Building 2B, Carl Vinson Medical Center

Project Details

Facilities Maintenance, Repair, & Modernization
VA Medical Center, Dublin, GA
Client: United States Department of
Veterans Affairs
Project Size: $2M – $5M

Project Description

This contract’s scope of work called for the removal and replacement of three indoor central station Air Handling Units (AHUs) as well as the installation of new exhaust fans, chilled water pumps, chilled water piping, hydronic piping, and humidifiers.  The project also included the replacement of ductwork, heat exchangers, and hydronic piping servicing these replacement air handler units.  Work also included the installation of new electrical home runs and panel boards to service all new upsized equipment.  Finally, work included the installation of all new DDC controls for the AHUs and associated equipment.

General construction work included the installation of new ceiling tiles and painting of the renovated mechanical rooms where the AHUs were located.  Plumbing work included the installation of new equipment drains to service the new equipment.

On this design-bid-build construction contract, Sergent Construction (SC) acted as the general contractor as well as self-performed the following trades:  demolition, HVAC, electrical, and plumbing.  In total, SC self-performed 85% of this project’s work.

Repair HVAC System and Building Envelope, Building 3413

Project Details

Facilities Maintenance, Repair, & Modernization
Ft. Devens, Massachusetts
Client: United States Army Corps of Engineers, New England District
Project Size: $2M – $5M

Project Description

This project’s scope of work involved the renovation and rehabilitation of the 30,000 SF High Security Intelligence Building 3413 located at Ft. Devens, Massachusetts.  This project included the removal and replacement of the existing HVAC system including HVAC DDC, lighting system, roofing system, and the repair/replacement of masonry exterior.  Also included was the interior carpet, paint, acoustical ceiling tile, and drywall.  Mold abatement for the entire facility was also completed.

The renovated HVAC system consisted of the removal and replacement of 48 VAVs, 2-850 MBTH Boilers, 150-ton air cooled chiller, and an entirely new return duct work system to convert the open plenum to a ducted return for increased system efficiencies.  In addition, work included the removal and replacement of the existing built-up bitumen roofing system with a new Single Ply 60 Mil PVC roofing system.  The performance specifications for this project were derived from LEED’s performance requirements for the new roofing and the HVAC systems.

Multipurpose Facility Renovations and New Fuel System at USCG Station

Project Details

Facilities Maintenance, Repair, & Modernization
Port Aransas, Texas
Client: United States Coast Guard Civil Engineering Unit, Miami
Project Size: $0M – $2M

Project Description

This project involved the renovation and repair of an existing 8,000 SF multipurpose facility and the removal and replacement of the station’s above ground fueling system located at the United States Coast Guard’s (USCG) Station, Port Aransas, TX.  Scope of work included the complete replacement of the facility’s existing heating, ventilation, and air conditioning (HVAC) and direct digital control (DDC) systems as well as the rehabilitation of the facility’s existing electrical and plumbing systems.  Extensive interior renovations were also done.

5E Remodel HVAC Upgrades

Project Details

Facilities Maintenance, Repair, & Modernization
VA Medical Center, San Diego, CA
Client: United States Department of
Veterans Affairs
Project Size: $0M – $2M

Project Description

This contract’s scope of work called for the removal and replacement of one 20,000 CFM Air Handling Unit (AHU) located in the 5th floor interstitial space of the La Jolla VA Medical center.  Additional work included installation of a duct silencer, new AHU chilled water piping, DDC controls, new hot water heating piping, and electrical home runs.  During construction, work included the installation or a temporary 20,000 CFM AHU from Sergent Constructions temporary AHU fleet in order to provide temporary cooling for the 5th floor east wing.

On this design-bid-build construction contract, Sergent Construction (SC) acted as the general contractor as well as self-performed the following trades:  demolition, HVAC, electrical, and plumbing.  In total, SC self-performed 90% of this project’s scope of work.

Replace Air Handling Units in Bldgs 1 & 23, Durham VA Medical Center

Project Details

Facilities Maintenance, Repair, & Modernization
Durham, NC
Client: Department of Veterans Affairs
Project Size: $2M – $5M

Project Description

For this design-bid-build firm fixed price contract Sergent Construction acted as general contractor and self-performed most of the on-site work.  This contract’s scope of work called for the removal and replacement of 10 Air Handling units, replacement of associated exhaust fans, electrical upgrades for the AHUs, chilled water piping, refrigeration piping, hot water piping, hot water pumps, humidifiers, chilled water pump, and hydronic accessories including steam to hot water heat exchangers.  New fan coils and ductwork systems were provided to service the laboratory areas.  The air handling units scheduled to be replaced covered a wide array of styles and configurations including indoor centration station air handling unit, DX Split System, and package units.  Work also included the removal and replacement of ceiling, drywall, and paint work throughout the facility.  The electrical scope of work includes electrical home runs, panel boards, and MCC breaker to service the new upsized equipment.  Additional work also included the installation of new DDC controls for the AHUs and AHU associated equipment.  Plumbing work included the installation of new equipment drains to service the new equipment.

Hurricane Isaac Damage Repairs

Project Details

Facilities Maintenance, Repair, & Modernization
USCG Station Grand Isle, Louisiana
Client: United States Coast Guard
Project Size: $0M – $2M

Project Description

This design-bid-build project scope of work involved repairing the USCG’s Station located in Grand Isle, LA after Hurricane Isaac caused flood and wind damage throughout the facility.  Sergent Construction (SC) performed work throughout the entire Station which included 24 housing units, the Engineering Building, WPB building, Swimming Pool structure, the Station Building, and the Unaccompanied Personnel Housing (UPH) facilities.

HVAC Storm Damage Repair at USCG Station

Project Details

Facilities Maintenance, Repair, & Modernization
Grand Isle, Louisiana
Client: United States Coast Guard
Project Size: $0M – $2M

Project Description

This design-build contract’s scope of work involved repairing additional storm damage at the Grand USCG Station caused by Hurricane Isaac.  Damage to the site included water damage from roof leaks and flooding as well as structural damage from hurricane force winds.  The work completed for this project included the removal and replacement of all the ductwork in 16 occupied USCG personal apartments, the repair of the standing seam metal roofing system, and the removal and replacement of two structural columns.  The removal and replacement of the ductwork within the 16 apartments required Sergent Construction personal to schedule the work around each apartment occupant’s daily schedule.  Sergent Construction also remove and re-install existing roof as necessary to ensure a weather tight seal.

Comprehensive Building Repairs

Project Details

Facilities Maintenance, Repair, & Modernization
Moffett Field, CA
Client: US Air Force National Guard
Project Size: $2M – $5M

Project Description

This construction project involved the complete interior and exterior renovations of five buildings and the re-roofing of 11 buildings.  The scope of work related to the exterior renovations included: installation of an underground high-voltage electrical distribution system, installation of a new emergency back-up power generator, installation of new underground communications and data systems, construction of a new parking lot including earthwork, paving, exterior lighting, landscaping, and concrete curbs and gutters.

Replace Air Handling Units, Building 1, D-Wing, Fayetteville VA Medical Center

Project Details

Facilities Maintenance, Repair, & Modernization
Fayetteville, North Carolina
Client: Department of Veterans Affairs
Project Size: $0M – $2M

Project Description

This project’s scope of work involved the removal and replacement of two 20,000 CFM indoor central station Air Handler Units (AHUs) and associated equipment, plumbing, and electrical work at the Fayetteville VA Medical Center’s D-Wing located in Building 1.  Work on this project included the installation of two new 20,000 CFM AHU’s, VFDs for both the AHUs and exhaust fans, intake louvers, and supply and return ductwork for the air handler units.  Also included was the installation of a high performance 3-coat epoxy floor coating in Building 1.

Work included the installation of an updated HVAC DDC to control system for the newly installed AHU’s, exhaust fans, and humidifiers.  The new DDC control system was tied into the Fayetteville VA Medical Center’s integrated digital building management systems or Building Automation System (BAS) control system.  In addition, new electrical feeders, circuit breakers, and panel boards for the upsized AHUs and Exhaust Fans were installed.

On this design-bid-build construction contract, Sergent Construction (SC) acted as general contractor as well as self-performed the following trades: demolition, HVAC, mechanical piping, temp AHU installation, temporary electrical, electrical, equipment rigging, carpentry, and concrete.  In All, SC self-performed 81% of this project’s scope of work.

Building 101 Renovations at USCG Station

Project Details

Facilities Maintenance, Repair, & Modernization
Mobile, AL
Client: United States Coast Guard Civil Engineering Unit, Miami, FL
Project Size: $2M – $5M

Project Description

This design-bid-build project involved the renovation of an existing electrical shop, medical clinic space, and office space in Building 101 at the USCG Station, Mobile, AL.  This included the demolition of the buildings existing architectural finishes and associated building systems as well as asbestos abatement.  New work included architectural finishes and caseworks, new electrical and lighting systems, and a new fire alarm system.

A new heating, ventilation, and air conditioning (HVAC) system was also installed including ductwork and refrigerant lines.  Plumbing, plumbing fixtures, drywall, paint, and metal stud framing was included