Project Details
Facilities Maintenance, Repair, & Modernization
NASA Armstrong Flight Research Center,
Edwards, CA
Client: National Aeronautics and Space Administration Armstrong (NASA)
Project Size: $2M – $5M
Facilities Maintenance, Repair, & Modernization
NASA Armstrong Flight Research Center,
Edwards, CA
Client: National Aeronautics and Space Administration Armstrong (NASA)
Project Size: $2M – $5M
This project’s scope of work involved the renovation and rehabilitation of NASA’s Research Hangar B4802 HVAC system. The existing HVAC system at the hangar consisted of nine direct evaporative cooling units mounted on 10’ tall structural steel frames. The existing HVAC system in its entirety was demolished and replaced.
The new HVAC system consisted of seven 35,000 CFM and 25,0000 CFM indirect direct evaporative coolers with and without gas heat. The AHUs were provided with factory installed and tested HVAC DDC systems to speed up project production. Once the AHUs were set, the HVAC DDC controls were tied into the existing Siemens HVAC DDC system and the base wide energy monitoring system. Additionally, entirely new supply and return ductwork was also installed on the exterior of the hangar to service the new AHUs. Existing louvers and duct penetrations were blocked off to allow for the new relief air dampers to provide the proper air changes required for aircraft hangars per the UFC.
Site work included the placement of seven new 18” thick CIP equipment pads to support the new AHUs and electrical equipment (MV transformer, MV switch, and distribution board). Site utility work included the installation of a new electrical substation to feed the AHUs which consisted of a 200A 12.47 KVA secondary switch, 1000 KVA MV Transformer (12.47 KVA to 480V), and one 1600A Distribution Board equipped with Square D energy meters for the line load and each circuit. The energy meters were integrated into the base wide energy management system for monitoring by NASA’s facilities department. Additional work included the installation of new electrical duct banks to feed the substation and AHUs, excavation, backfill, paving, new high-pressure gas system including a utility meter to provide gas for the AHU Gas Heaters, gas pressure reducing valves, and lead paint abatement on existing structural steel. All the above work was performed on an active flight line and required the use of FOD checks going into and out of the project site.
The electrical scope of this project included running new electrical service from the substation located on the flight line to the AHUs located adjacent to the hangar. The plumbing scope of work for this project included the installation of new domestic/potable water branch lines and main line to feed the AHU make-up water. New sanitary sewer branch and main lines were also installed to service the new AHUs drains.
On this design-bid-build construction contract, Sergent Construction acted as the general contractor overseeing construction as well as self-performing the following trades: demolition, HVAC, equipment rigging, and mechanical piping. In total, SC self-performed 85% of this project’s work.
Facilities Maintenance, Repair, & Modernization
VA Medical Center, Cheyenne, WY
Client: Department of Veterans Affairs
Project Size: $2M – $5M
This project’s scope of work involved the complete renovation and rehabilitation of the Cheyenne VA Medical Center’s central chilled water plant located in the basement of the Clinical Additions building. The existing chilled water plant consisted of 3 chillers, 3 cooling towers, and the associated chilled water and condenser pumps. In order to meet the needs of an ever-expanding Cheyenne VA Medical Center, the VA needed to expand the capacity of the chilled water plant from 900 to 1,200 tons of cooling. The existing chilled water plant consisted of two existing 250-ton chiller and one new 400-ton variable speed magnetic bearing chiller that was installed by SCS on a previous chilled water plant rehabilitation project 6 month’s prior.
Work included the replacement of the two remaining 250-ton cooling towers with two new 400-ton cooling tower to meet the cooling needs of the 2 new 400-ton variable speed magnetic bearing chillers. The existing 400-ton cooling tower installed 6 months prior by SCS was retained and reinstalled on a new structural steel frame. Additional installed equipment included a side stream filtration system for the condenser water, 10” pipe diameter air separator, expansion tank, automated water treatment system, three new vertical 25 HP Condenser Water Pump, 50 HP base mounted Chilled Water Pump, precast 7,180-gallon condenser water cistern tank, and the relocation and reutilization of two existing 50 HP base mounted chilled water pumps, and three new vertical inline 15 HP Chilled Water Pumps.
All new mechanical equipment including chiller, cooling towers, and pumps were powered by variable speed drives to ensure maximum system efficiency. In order to make the entire chilled water plant more efficient, a 522-ton plate and frame heat exchanger was salvaged from the site and reinstalled along with new variable frequency drives on the cooling tower, pumps, and chiller. Furthermore, all existing chilled and condenser water piping inside the plant was completely removed and replaced with schedule 40 14”, 12”, 10”, & 8” welded steel pipe. All the new indoor and outdoor mechanical piping was insulated with mineral fiber insulation that included a separate PVC protective jacket for areas exposed to damage in the mechanical room.
Additional mechanical work included the installation of 8” future chilled water supply and return site piping throughout the basement and service tunnels of the entire campus. Work also included the installation of a new Reverse Osmosis water treatment system to supply soft (mineral free) filtered water to the existing penthouse AHU humidifiers. A new 60 MIL TPO roofing system for the pharmacy area where the cooling towers were located was also installed as part of this project’s scope of work. SCS also replaced the existing chilled water plant DDC control system with a new Chiller Plant Optimization (CPO) equipped HVAC DDC system from Johnson Controls, Inc. The CPO system consisted of the installing 8 venturi flow meters and four motorized control valves along with all new sensors and controllers for every piece of equipment in the plant. The new JCI HVAC DDC with CPO allowed for accurate control, energy metering, and energy optimization of the chilled water plant all while being interfaced with the existing NIAGRA building management system (BMS).
The electrical scope of work included new electrical feeders, electrical service, circuit breakers, panel boards, motor control centers to support the new plant. Structural work included the design and construction of three new cooling tower structural steel frames to support the three 400-ton BAC cooling towers. Additional structural work included the installation of cast in place concrete pads for all new and reutilized equipment including chiller, heat exchanger, pumps, and side steam filtration unit.
On this design-bid-build, firm fixed price construction contract, Sergent Construction Services acted as general contractor as well as self-performed 80% of the following trades: demolition, cistern installation, equipment rigging, structural steel, HVAC, mechanical piping, plumbing, carpentry, and cast in place concrete.
Facilities Maintenance, Repair, & Modernization
NASA Armstrong Flight Research Center,
Edwards, CA
Client: National Aeronautics and Space Administration (NASA)
Project Size: $5M – $8M
This project’s scope of work involved the complete renovation and rehabilitation of the NASA’s Mission Control electrical system. The removed Mission Control electrical system consisted of antiquated manual transfer switches that operated two redundant Uninterruptable Power Source (UPS) located in Bldg. 4848. The two existing 400KW UPSs contained only 15 minutes of battery life and were insufficient to handle Mission Control’s increased electrical loads. Additional electrical equipment removed include 3-400A Panelboards, one 600A Panelboard, two 1200A Switchgears, and all associated feeders and branch circuits.
The revitalized Mission Control electrical system consisted of new and cutting-edge critical power system equipment. This included five new 150/300 KVA Power Distribution Units (PDU) with integrated digital building management systems or Building Automation System (BAS) controls including touchscreen graphical user interface control panels. In addition, two new 450 KW UPS’s with 30 minutes of battery life and touch screen graphical user interface BAS controls were also installed. These two were provided to ensure that NASA’s Mission Control had ample time to safely terminate active missions in the event of a power failure.
In order to handle the increased cooling loads of the electrical panelboards and UPSs housed in Bldg. 4848, the entire HVAC system for this portion of the building was removed and replaced. This included all new ductwork. Site work also included the installation of 13 free standing structural steel frames to support new above grade emergency power electrical feeders for mission controls. The fire alarm in Bldg. 4848 was also removed, replaced, and tied into the base wide fire alarm system. Finally, due to this project’s critical nature, an extensive engineering verification and testing of all newly installed equipment was performed. This included a new and existing electrical system arc flash and power coordination study.
In order to provide a redundant emergency power source for mission control, the two UPS’s were tied to line power through two static transfer switches. This allowed the system to operate on both utility and E-power while providing redundant UPS power if the primary UPS wasn’t functioning. New electrical switch gear consisted of three 800A Distribution Boards, one 400A Distribution Board, one 30 KVA transformer, rack-in 800A electronic breakers, and two 1200A Switchgears. Entirely new electrical feeders and branch circuits were provided throughout the facility to feed all new and affected existing electrical systems.
The installation of the new critical power electrical equipment increased cooling loads on the affected buildings. In order to handle the increased cooling loads, the entire HVAC system in Bldg. 4848 where the electrical panelboard and UPSs are housed was completely removed and replaced. The new HVAC system consisted of 10-ton and 25-ton packaged heat pumps with economizers placed on CIP reinforced concrete equipment pads adjacent to Bldg. 4848. The entire ductwork system in the building was removed and replaced with new. The packaged heat pumps were equipped with on-board HVAC DDC controls to allow for integration of the units into the campus wide HVAC DDC/BAS. The electrical feeders for these units were routed from the new electrical switchgear installed in Bldg. 4848. Additional HVAC system installation included the installation of three mini split systems ranging in size from 3 to 4 tons in Rm 1002 of Bldg. 4800 where a new PDU and existing telecommunication equipment was located.
Site work included the installation of 13 free standing structural steel frames to support the new emergency power electrical feeders for mission controls above grade. The new feeders included eight 4” RGS Conduits with #600 mcm & 1/0 ground conductors and three 1” RGS conduits with three #6 AWG and #10 AWG ground Conductors). Additional work included the installation of contractor designed structural steel brackets and framework to support the new electrical feeders from the exterior of the Mission Control facility.
The project scope of work also included the integration of all new electrical gear into the existing Utility Monitoring and Control system (BAS). Additionally, all electrical distribution boards were equipped with energy meters which were integrated into the base wide energy management system for monitoring by NASA’s facilities department. Architectural renovations included the installation of new doors and frontal opening in Bldg. 4848 to allow for proper egress. Furthermore, the entire fire alarm in Bldg. 4848 was removed and replaced with a new system that is properly tied into the base wide Fire Alarm & MNS system.
Finally, additional quality assurance requirements included the factory start-up for all installed electrical switchgear, PDU’s, Panelboard, and UPS’s. The quality of the electrical system installation was further verified by a third-party InterNational Electrical Testing Association (NETA) accredited inspection firm. Furthermore, the entire new electrical system was put through a 24-hour load bank functional performance test to verify system functionality and battery performance.
On this design-bid-build construction contract, Sergent Construction (SC) acted as general contractor overseeing construction as well as self-performed the following trades: demolition, HVAC, equipment rigging, carpentry, electrical, and mechanical piping. In total, SC self-performed 75% of this project’s work.
Facilities Maintenance, Repair, & Modernization
Ft Campbell, KY
Client: : United States Army Corps of Engineers
Project Size: $5M – $10M
This project involved the renovation and rehabilitation of Ft. Campbell High School’s 100,000 SF campus located in Ft. Campbell, KY. This project’s scope included the removal and replacement of existing HVAC system, numerous ceilings, and various lighting systems. The existing HVAC system at the school was in disrepair after 30 years of use coupled with poor maintenance. The new HVAC system consisted of one new 365-ton chiller, an entirely new chilled water piping system, 65 fan coils units, 5 inside air handlers, new ductwork throughout, and nine roof top air handlers. The chilled water system was comprised of redundant 30 HP chilled water pumps and 365-ton air cooled chiller all equipped with variable frequency drives for optimum efficiency. In order to integrate the new HVAC system with portion of the old system that were not replaced, an entirely new Delta Controls HVAC DDC control system was installed in both the existing and renovated portions of the school. The DDC control system was also linked to the base wide BACnet system allowing for centralized monitoring and control of the facility by Ft. Campbell’s public works department.
Additional work included the removal and replacement of the existing built-up bitumen roofing system with a new Single Ply 60 Mil PVC roofing system. The new roofing system included the installation of 5” of insulation overtop of ½” gypsum cover board in order to meet the project’s LEED derived thermal and light reflectance performance specifications.
Site work for this project included the installation of underground electrical, underground chilled water line, concrete slab on grade, and site fencing for the new chilled water plant which was located separate from the school building. Construction, repair, and alteration of plumbing systems including the installation of new equipment drains and roof drains.
The electrical scope of this project consisted of electrical rehabilitations including 2 new main panels to feed the various newly installed HVAC equipment. Additional work included the removal and reinstallation of approximately 1,000 light fixtures throughout the interior and exterior of the school. Along with the installation of lights a new theatrical lighting control system was installed along with new theatrical lights. Throughout the project’s life cycle SCS’s electrical team was requested to troubleshoot and repair many electrical devices and circuits that were in disrepair in addition to our original contracted work.
On this design-bid-build construction contract, Sergent Construction acted as general contractor overseeing construction as well as self-performed the following trades: electrical, temporary electrical, temporary cooling demolition, finish HVAC, equipment rigging, structural steel installation, and site work. In total, SCS self-performed 60% of this project’s work.
Facilities Maintenance, Repair, & Modernization
VAMC Gainesville, FL
Client: Department of Veterans Affairs
Project Size: $5M – $8M
This project included the installation of a new 80,000 cubic feet per minute (CFM) outdoor central station air handler unit (AHU) located on the second-floor roof. In order to support the new AHU, an entirely new structural steel platform was erected with stairs and walkways around the exterior. Once the unit was installed, a new mechanical penthouse was constructed around the AHU to protect the AHU and associated systems from the elements.
This project also included the removal and installation of a 21,000 CFM indoor central station AHU. Work also included installation of new single coil VAV’s, supply and return ductwork throughout the renovated area, heating hot water piping system with heat exchanger, new DDC controls, new fire alarm devices, and abatement of asbestos.
Additional work included the installation of 97 new single coil VAV’s on five floors of the main hospital with services provided to admin areas, patient rooms, CLC, laboratories, and surgery suites. New supply ductwork was installed throughout the renovated floors to allow the existing dual duct system to be converted to a supply and return ductwork system. Additional work included the installation of heating hot water piping system to supply heat to the new VAV’s. The heating hot water system was supplied with heated water through the installation of a steam to hot water heat exchanger system. This included a skid mount parallel heat exchangers, parallel pumps, and HVAC DDC.
Work also included the removal and replacement of ceilings, installation of new lights, partition walls, drywall, paint, roofing patch and repair, core drilling, fire caulking, and large-scale abatement of asbestos-containing materials (ACM) pipe insulation and duct mastic. Additional work included the installation of new DDC controls for all installed equipment including AHUs, pumps, heat exchangers, VAVs, and glycol systems. All new equipment was equipped with VFDs drives to ensure that all equipment would operate at max efficiency given the building loads. Lastly, new fire alarm devices, FACPs, and plumbing were installed to support the new VAVs and AHUs. In all, over 60,000 SF of hospital floor space was renovated.
For this design-bid-build contract, SCS acted as the general contractor as well as self-performed the following trades; demolition, mechanical piping, ductwork, electrical, and equipment installation. In total, SCS self-performed 90% of the project’s scope of work.
Facilities Maintenance, Repair, & Modernization
VAMC Gainesville, FL
Client: Department of Veterans Affairs
Project Size: $2M – $5M
This project involved the installation of one custom indoor centration station 15,000 Cubic Foot Per Minute (CFM) Air Handler Units (AHU) to service the VA hospital’s laboratory and associated administrative area. The project also called for the installation of a 14,000 CFM rooftop AHU to service the sterile storage and Sterile Processing Department (SPD) areas of the hospital. The facilities existing HAVC DDC and electrical systems were expanded to facilitate the addition of the equipment. Additional rooftop work included the installation of a chilled water plant to support the new roof mounted AHU.
The chilled water plant consisted of parallel 15 HP pumps, VFDS, expansion tanks, air separator, chilled water piping, and a 150-ton air cooled chiller. New structural steel platforms, complete with ladders and walkways, were installed to support both the new rooftop AHU and 150-ton air cooled chiller. Also included was the installation of a steam to hot water heat exchanger system to provide hot water to the VAV
In addition to the installation of a 150 Ton Air Cooled Chiller and associated chilled water pumps, piping, hydronic accessories, and structural steel platforms, a new heating hot water system was also installed in the laboratory and SPD to service the 40 new VAVs. New supply and return ductwork systems were also installed in the mechanical rooms, laboratories, admin spaces, and SPD. Lastly, new ceilings, lighting, paint, drywall partitions were provided for the laboratory and SPD. This project also included the installation of new roofing systems in the renovated areas. In addition, extensive abatement of asbestos-containing materials (ACM) was done for ACM materials found in the pipe insulation and duct mastic in the laboratory and SPD areas.
For this design-bid-build contract, SCS acted as the general contractor as well as self-performed the following trades; demolition, mechanical piping, ductwork, electrical, and equipment installation. In total, SCS self-performed 85% of the project’s scope of work.
Facilities Maintenance, Repair, & Modernization
VA Medical Center, Cheyenne, WY
Client: Department of Veterans Affairs
Project Size: $0M – $2M
This project’s scope of work involved the renovation and rehabilitation of a portion of the Cheyenne VA Medical Center’s central chilled water plant located in the basement of the Clinical Additions Building. The existing chilled water plant consisted of 3 chillers, 3 cooling towers, and the associated chilled water and condenser pumps. In order to meet the needs of an ever-expanding Cheyenne VA Medical facility, this project’s scope of work included the removal of one existing 250-ton chillers and replacing it with a 400-ton variable speed magnetic bearing chiller. Work also included the replacement of the existing 250-ton cooling tower and structural framework to support a new 400-ton cooling tower and framework to meet the cooling needs of the new 400-ton variable speed magnetic bearing chiller.
Additional installed equipment included a side stream filtration system for the condenser water, 25 HP Condenser Water Base Mounted Pump, 25 HP Chilled Water Base Mounted Pump, 2-50 HP Secondary Chilled Base Mounted Water Pumps, and 2-20 HP Water Side Heat Exchanger Base Mounted Water Pumps. In order to make the entire chilled water plant more efficient a 522-ton plate and frame heat exchanger was installed along with variable frequency drives on the cooling tower, water pumps, and chiller. In total, the installed chilled water capacity on this project was 922 tons when taking into consideration the capacity of both the chiller and heat exchanger.
In order to tie together all the new and replaced equipment, all the existing chilled and condenser water piping between these pieces of equipment was removed and replaced with schedule 40, 8” welded black iron pipe. All the new indoor and outdoor mechanical piping was insulated with mineral fiber insulation that included a separate PVC protective jacket and aluminum jacket for outdoor insulation. The pumps were insulated with custom fabricated insulated pump boxes which allowed for easy access for future maintenance and replacement.
Work on this project also included a complete upgrade to the existing chilled water plant’s HVAC DDC system which included the installation of 4 venturi flow meters, nine 8” motorized control valves, and new sensors and controllers necessary to operate the new equipment. The new control system allowed for accurate control and energy metering of the chilled water plant during operation via flow meters and temperature sensors. The control system was also tied into the facilities existing building management system. The electrical scope of work on this project included new electrical feeders, circuit breakers, panel boards, and motor control centers to allow for the installation of the upsized replacement mechanical equipment and new mechanical equipment.
On this design-bid-build construction contract, Sergent Construction (SC) acted as general contractor and self-performed the following trades: demolition, equipment rigging, HVAC, mechanical piping, carpentry, and concrete. In total, SC self-performed over 80% of this project’s work.
Facilities Maintenance, Repair, & Modernization
Fort Irwin National Training Center, Fort Irwin, CA
Client: United States Army Corps of Engineers
Project Size: $0M – $2M
This project’s scope of work involved the complete renovation and rehabilitation of the HVAC systems in Buildings 20, 310, and 400 at the Ft. Irwin National Training Center located in Ft. Irwin, CA. Building 20 is located at the Barstow-Daggett Airport approximately 30 miles from post and is the Army’s Fire Station that services their airborne cavalry training unit. Building 400 is Ft. Irwin’s fire station while Building 310 is the MWR’s movie theater facility. The scope of work for each building is as follows:
In addition, new Heating, Ventilation and Air Conditioning (HVAC) Direct Digital Control (DDC) systems were installed in each of the 3 buildings. The HVAC DDC work consisted of a new HVAC DDC front end, controllers, and all migration of existing control components for each building into the new HVAC DDC front end. The new HVAC DDC front end was then tied into the existing campus wide Niagara Building Management Systems.
Additional work on Bldg. 20 included the installation of a two bay 3000 CFM vehicle exhaust system with automated controls as well as automatic vehicle connection/disconnection system which allowed for the fire trucks to automatically connect/disconnect to the exhaust extractors upon entering and exiting the bays. The installation of this system put the fire station to in compliance with Environmental Protection Agency 2007 Highway Diesel Rule (EPA07); NFPA 1500 (Section 9); OSHA; the International Code Council (Building Code); and United States Fire Administration’s Assistance to Firefighters Grant Program Guidelines. Lastly, new electrical service including switchgear, conduits, disconnects, and wire was installed to support the new HVAC equipment. At the conclusion of construction, a complete system test and balance was performed followed by enhanced HVAC Commissioning by a third-party commissioning agent.
Bldg. 310’s scope of work included the complete renovation of the movie theater’s HVAC system. Work included the demolition of the existing chiller, chiller condensing unit, central station AHUS, and rooftop package units. The new system consisted of a new chilled water yard with cast in place concrete pad and CMU screen walls, 60 Ton Air Cooled York Chiller, 2 HP in line chilled water pump, 1.5 HP inline heating hot water pump, two 7.5 Ton Rooftop Packaged Heat Pumps with seismic curbs, two custom indoor central stations AHUS for heating and cooling ratted at 27 Tons Cooling/270 MBH Heating at 7,300 CFM and 5,200 CFM with 20 tons cooling and 194 MBH Heating, supply and return air systems, chilled water supply/return piping, heating hot water supply/return piping, chilled water and hot water treatment system, and mechanical insulation. Additional work included a completely new BACNET HVAC DDC system to provide control of the entire HVAC system including existing equipment and was integrated directly into the base wide BMS. All new equipment was equipped with VFDs to ensure efficient operations at all building heating and cooling loads. Furthermore, new electrical service including switchgear, disconnects, conduit, and wire was provided for all new HVAC equipment and HVAC DDC control panels. Existing ductwork that was to remain was cleaned to NADAC standards. The existing Fire Alarm system was also updated with new fire alarm devices and programming to allow for the integration of the new HVAC equipment. At construction’s conclusion the entire system was test and balanced followed by third party enhanced HVAC Commissioning.
Bldg. 400’s scope of work included the complete renovation of the fire station HVAC system. Work included the demolition of the two existing DX split air handlers, three updraft furnaces, VAVs, and two Rooftop Evaporative Coolers. The new HVAC system consisted of new two new rooftop evaporative coolers, three VAV’s with electric heat, supply/return air systems, ventilation/exhaust duct, and a 10-ton DX split System with multistage compressors and VFD on the AHU. All existing ductwork that was left in place was cleaned to NADAC standards. Lastly, a completely new BACNET HVAC DDC system with energy meters was installed to provide control of the entire HVAC with integration directly into the base wide BMS. Also, new electrical service including switchgear, conduits, disconnects, conduit, and wire was installed to support the new HVAC equipment. Additionally, energy meters were installed on the building’s main feeders to monitor and log facility power consumption to allow public works to better manage the facility. An arc flash and power coordination study were also provided for the new and existing electrical infrastructure. At construction’s conclusion, a complete system test and balance was performed followed by enhanced HVAC Commissioning by a third-party commissioning agent.
On this design-bid-build construction contract Sergent Construction acted as general contractor as well as self-performed the following trades: demolition, HVAC, mechanical piping, ductwork, equipment rigging, and carpentry. In total, SC self-performed 75% of this project’s work.
Facilities Maintenance, Repair, & Modernization
Defense Distribution Depot San Joaquin, Tracy, CA
Client: Defense Logistics Agency
Project Size: $0M – $2M
This project’s scope of work involved the removal and replacement of the Makeup Air Units (MAU) and Power Roof Ventilator (PRV) exhaust fans for the 160,000 SF Warehouse Number 28 located at the Defense Distribution Depot San Joaquin, Tracy, CA. The existing HVAC system consisted of 10 rooftop evaporative coolers for supply air and ten rooftop exhaust fans for the return air. The existing supply ductwork was deficient due to rust and degradation.
The revitalized and renovated HVAC consisted of ten new custom fabricated stainless-steel rooftop evaporative AHUs ranging in size from 8,000 CFM to 13,000 CFM and ten rooftop exhaust fans rated at 12,000 CFM. The AHU’s were constructed of stainless steel to improve the unit’s operational life span. Additionally, the units were equipped with hot water coils or gas heaters to allow the units to serve both the buildings cooling and heating needs. Each unit was custom built which enabled the units to fit the existing roof curbs and supports. In order to increase system efficiency, the AHU’s were also equipped with VFDs. All AHU plenums and supply ductwork were removed and replaced. In addition, a new HVAC DDC system was also installed
To ensure efficient operation, an entirely new HVAC DDC system was installed to control both the AHUs and exhaust fans. The HVAC DDC system consisted of new HVAC Sequence of Operations for the AHUs and exhaust fans with controls provided via BACNET controllers tied back to the facilities BACNET BAS front end. The new HVAC DDC system included new energy meters for both the electrical and natural gas systems feeding the AHUs. All HVAC DDC, motor starters, and electrical disconnects were contained in NEMA 4X stainless steel enclosures to ensure system longevity and weather resistance. New duct smoke detectors were provided for each AHU and tied back into the building’s fire alarm system. Additional work included the installation of new domestic water lines, drain lines, heated hot water supply/return, and mechanical insulation to service the new AHUs.
All existing building utilities that were in the way of construction including electrical, lighting, fire protection, and fire alarm were reworked and/or relocated to allow for system installation. New electrical home runs and circuit protections was provided for all installed equipment. The new and existing electrical systems all underwent an arc flash and power/short-circuit coordination study. Once the expected short-circuit currents are known, a protection coordination study is performed to determine the optimum characteristics, ratings, and settings of the power system protective devices.
On this design-bid-build construction contract, Sergent Construction (SC) acted as general contractor overseeing construction as well as self-performed the following relevant trades: electrical, demolition, HVAC, equipment rigging, mechanical piping, and ductwork R&R. In total, SCS self-performed 85% of this project’s work.
Facilities Maintenance, Repair, & Modernization
Schriever Air Force Base, CO
Client: Department of the Air Force
Project Size: $0M – $2M
This project’s scope of work involved the removal and replacement of three 225 tons air cooled chillers at the US Air Force’s Space Command at Schriever AFB. Additional site work included the installation of larger Cast in Place (CIP) concrete equipment pads to accommodate the larger chillers. The new BACnet equipped chillers were tied into the existing HVAC DDC with a new HVAC Sequence of Operations, control points, and alarms. Additional work included the installation of a temporary chiller during construction to ensure the requisite HVAC system redundancy requirements for the facility were met.
On this design-bid-build construction contract, Sergent Construction (SC) acted as general contractor as well as self-performed the following trades: demolition, mechanical, & electrical. In total, SCS self-performed 95% of this project’s scope of work.
Facilities Maintenance, Repair, & Modernization
VA Medical Center, Cheyenne, WY
Client: Department of Veterans Affairs
Project Size: $0M – $2M
As part of the VA’s commitment to increase energy efficiency and upgrade their infrastructure, the VA Medical Center, Cheyenne, WY constructed a state-of-the-art combined heat and power plant. This plant’s purpose was to reduce the facility’s overall efficiency by allowing the medical center to produce its own power and use the heat generated from the facility’s generators to heat the medical center. In order to allow the facility’s plant to operate more efficiently, SCS’s contract scope of work called for the removal of one 150 HP Cleaver Brooks boiler and the installation of two new 3,000 MBH ultra high efficiency condensing boilers. The purpose of these new condensing boilers was to augment the heat generated by the combined heat and power plant, on an as needed basis, to allow the campus’ hot water heating system to operate at the proper heating hot water loop temperature thereby optimizing system efficiency.
Work also included the expansion of the heating hot water loop in the hospital to accommodate the installation of two new domestic water heat exchangers to provide hot water for two patient wings at the hospital. Additionally, the facility BMS and HVAC DDC were tied into the new boilers and heat exchangers to allow for proper control and monitoring by the VA Medical Center’s facilities department.
On this firm fixed price design-bid-build construction contract Sergent Construction Services acted as the general contractor and in addition self-performed the demolition, HVAC, mechanical, and plumbing. In total, SCS self-performed 90% of this task order’s scope of work and this contract’s scope of work.
Facilities Maintenance, Repair, & Modernization
VA Medical Center, Dublin, GA
Client: United States Department of
Veterans Affairs
Project Size: $2M – $5M
This contract’s scope of work called for the removal and replacement of three indoor central station Air Handling Units (AHUs) as well as the installation of new exhaust fans, chilled water pumps, chilled water piping, hydronic piping, and humidifiers. The project also included the replacement of ductwork, heat exchangers, and hydronic piping servicing these replacement air handler units. Work also included the installation of new electrical home runs and panel boards to service all new upsized equipment. Finally, work included the installation of all new DDC controls for the AHUs and associated equipment.
General construction work included the installation of new ceiling tiles and painting of the renovated mechanical rooms where the AHUs were located. Plumbing work included the installation of new equipment drains to service the new equipment.
On this design-bid-build construction contract, Sergent Construction (SC) acted as the general contractor as well as self-performed the following trades: demolition, HVAC, electrical, and plumbing. In total, SC self-performed 85% of this project’s work.
Facilities Maintenance, Repair, & Modernization
Ft. Devens, Massachusetts
Client: United States Army Corps of Engineers, New England District
Project Size: $2M – $5M
This project’s scope of work involved the renovation and rehabilitation of the 30,000 SF High Security Intelligence Building 3413 located at Ft. Devens, Massachusetts. This project included the removal and replacement of the existing HVAC system including HVAC DDC, lighting system, roofing system, and the repair/replacement of masonry exterior. Also included was the interior carpet, paint, acoustical ceiling tile, and drywall. Mold abatement for the entire facility was also completed.
The renovated HVAC system consisted of the removal and replacement of 48 VAVs, 2-850 MBTH Boilers, 150-ton air cooled chiller, and an entirely new return duct work system to convert the open plenum to a ducted return for increased system efficiencies. In addition, work included the removal and replacement of the existing built-up bitumen roofing system with a new Single Ply 60 Mil PVC roofing system. The performance specifications for this project were derived from LEED’s performance requirements for the new roofing and the HVAC systems.
Work also included new hydronic heating hot water piping, a new HVAC DDC Controls system, boiler feed pumps, and the addition of heat recover coils and pumps. The rehabilitation of the existing air handling units included the installation of VFD motors, HVAC DDC, and new run around coil heat recovery systems. The new DDC Controls system was linked to the base wide BACnet system allowing for centralized monitoring and control of the facility by Ft. Deven’s Public Works department. Major exterior up-grades also included a new roof and exterior finishes.
Additional work included the removal and replacement of the existing built-up bitumen roofing system with a new Single Ply 60 Mil PVC roofing system. The new roofing system included the installation of 5” of insulation overtop of ½” gypsum cover board in order to meet the project’s LEED derived thermal and light reflectance performance specifications. Work for this project also included the repair of the building’s exterior masonry veneer which was damaged due to water intrusion and freezing of the water during the harsh winters which caused cracking of the veneer. Masonry restoration work included a complete cleaning of the masonry exterior, tuck point of damaged blocks and mortar joints, and complete replacement of the damaged masonry veneer in select areas.
The electrical scope of this project consisted of electrical service for the new equipment as well as the removal and reinstallation of approximately 550 light fixtures throughout the interior of the intelligence building. Throughout the project’s life cycle, SCS’s electrical team was requested to troubleshoot and repair many electrical devices and circuits that were in disrepair in addition to our original contracted work.
The performance specifications for this project were derived from LEED’s performance requirements for new roofing and HVAC systems. This project’s roofing system was LEED eligible under Sustainable Site Credit 7.2 and Materials and Resources Credit 4.1. The new HVAC system installed on this project consisted of ultra-efficient equipment and had to be commissioned by a third-party commissioner pursuant to LEED EA Prerequisite 1. In addition, SCS voluntarily implemented a strict Waste Management Plan that successfully diverted 50% of the construction waste generated on-site from going to local landfills making it eligible for a LEED points under LEED Materials and Resource Credit 2.1. SCS’s successful waste management plan was based on LEED’s approved Source Separated Method used in conjunction with recycling and donations of materials to local charitable organizations for reuse.
On this project, Sergent Construction Systems self-performed approximately 70% of the work. Some of the trades that were self-performed included electrical, demolition, HVAC, equipment rigging, mold abatement, mechanical piping, lighting, carpentry, and HVAC DDC controls.
Facilities Maintenance, Repair, & Modernization
Port Aransas, Texas
Client: United States Coast Guard Civil Engineering Unit, Miami
Project Size: $0M – $2M
This project involved the renovation and repair of an existing 8,000 SF multipurpose facility and the removal and replacement of the station’s above ground fueling system located at the United States Coast Guard’s (USCG) Station, Port Aransas, TX. Scope of work included the complete replacement of the facility’s existing heating, ventilation, and air conditioning (HVAC) and direct digital control (DDC) systems as well as the rehabilitation of the facility’s existing electrical and plumbing systems. Extensive interior renovations were also done.
Site work also included the removal and replacement of the station’s above ground fueling system. The existing 500-gallon gasoline Con-Vault fuel tank was replaced with a new 1,000-gallon Con-Vault fuel tank. The existing fuel system piping was also removed and replaced with stainless steel piping. In addition, new filter vessels were added to the fuel system in conjunction with the removal and replacement of the fuel systems hose reels and dispensers.
The HVAC work also included the complete removal and replace of all supply, return, and exhaust ductwork, installation of new condensers and air handlers, exhaust fans, and the installation of zero clearance grease ductwork for the kitchen hoods. Additional work on this project included paint and flooring throughout the 8,000SF facility, new drywall ceilings, drywall finishing, complete bathroom demolition and rehabilitation with the installation of new vanities, shower stalls, plumbing, and plumbing fixtures in the facility’s 9 restrooms.
On this design-bid-build construction project, Sergent Construction Services acted as the general contractor and self-performed 75% of the work including demolition and HVAC installation as well as all work related to the fuel system, plumbing, electrical, and carpentry efforts.
Facilities Maintenance, Repair, & Modernization
VA Medical Center, San Diego, CA
Client: United States Department of
Veterans Affairs
Project Size: $0M – $2M
This contract’s scope of work called for the removal and replacement of one 20,000 CFM Air Handling Unit (AHU) located in the 5th floor interstitial space of the La Jolla VA Medical center. Additional work included installation of a duct silencer, new AHU chilled water piping, DDC controls, new hot water heating piping, and electrical home runs. During construction, work included the installation or a temporary 20,000 CFM AHU from Sergent Constructions temporary AHU fleet in order to provide temporary cooling for the 5th floor east wing.
On this design-bid-build construction contract, Sergent Construction (SC) acted as the general contractor as well as self-performed the following trades: demolition, HVAC, electrical, and plumbing. In total, SC self-performed 90% of this project’s scope of work.
Facilities Maintenance, Repair, & Modernization
Durham, NC
Client: Department of Veterans Affairs
Project Size: $2M – $5M
For this design-bid-build firm fixed price contract Sergent Construction acted as general contractor and self-performed most of the on-site work. This contract’s scope of work called for the removal and replacement of 10 Air Handling units, replacement of associated exhaust fans, electrical upgrades for the AHUs, chilled water piping, refrigeration piping, hot water piping, hot water pumps, humidifiers, chilled water pump, and hydronic accessories including steam to hot water heat exchangers. New fan coils and ductwork systems were provided to service the laboratory areas. The air handling units scheduled to be replaced covered a wide array of styles and configurations including indoor centration station air handling unit, DX Split System, and package units. Work also included the removal and replacement of ceiling, drywall, and paint work throughout the facility. The electrical scope of work includes electrical home runs, panel boards, and MCC breaker to service the new upsized equipment. Additional work also included the installation of new DDC controls for the AHUs and AHU associated equipment. Plumbing work included the installation of new equipment drains to service the new equipment.
Due to the critical nature of AHU 52 and lack of redundancy SCS provided 20,000 CFM temporary AHU from our fleet of temporary AHUs in order to allow for this AHU to be replaced while leaving the hospital fully operational.
On this design-bid-build construction contract, Sergent Construction (SC) acted as general contractor overseeing construction as well as self-performed the following relevant trades: demolition, HVAC, electrical, and plumbing. In total, SCS self-performed 80% of this contract’s scope of work.
Facilities Maintenance, Repair, & Modernization
USCG Station Grand Isle, Louisiana
Client: United States Coast Guard
Project Size: $0M – $2M
This design-bid-build project scope of work involved repairing the USCG’s Station located in Grand Isle, LA after Hurricane Isaac caused flood and wind damage throughout the facility. Sergent Construction (SC) performed work throughout the entire Station which included 24 housing units, the Engineering Building, WPB building, Swimming Pool structure, the Station Building, and the Unaccompanied Personnel Housing (UPH) facilities.
Work performed in each area is outlined below:
Housing Units (RPFN): Replace water damaged roof insulation as necessary in all 24 housing units. Reseal roof penetrations in 24 units. Replace flashing at wall and roof joints in all 24 units. Replace water damaged drywall and paint in all 24 housing units. Remove and replace wood laminate flooring in all 24 housing units including VCT at the entryways. Repair two 10”x10” wood columns that were both water and termite damaged. Replace missing exterior wall panels and siding to match original. Reseal all exterior windows and door frames on the outside perimeter of all housing units. Clean, lubricate, and refurbish ground floor storage access doors including frames and hardware. Remove cork flooring found throughout the housing facilities and replace with VCT. Replace accordion storm shutters and Plexiglas in several units. Remove and replace portions of the HVAC ducts and registers in all 24 housing units that were damaged due to moisture. Replace T1-11 wood siding in ground floor storage areas and leave areas clean and unfinished.
RPFN Buildings 104, 110, & 113: SC performed a noninvasive roof inspection and found the standing seam roofs ridge cap gasket system wasn’t completely installed per the original roof plan. USCG gave SC a follow-on and separate contract to remove and re-install existing roof as necessary to ensure a weather tight seal.
WPB Building: Replace damaged overhead garage door including channels and hardware. Replace damaged and missing flashing that connects flat roof to wall. Caulk and seal all upstairs windows and horizontal seams between 1st and 2nd floors. Replace 3 downspouts and gutter system on the east and north walls.
Engineering Building: Replace damaged overhead garage door, including channels and hardware. Repair two double door frame connections to the building. Repair additional overhead frame connections to wall.
Swimming Pool: Replace 5’ tall decorative fencing and access gate.
Station Building: Repair hurricane shutters and replace gutter downspout.
UPH Building: Replace water damaged drywall and paint throughout building. Seal gaps in roof flashing. Seal all hurricane shutters and replace ceiling in one carport.
On this design-bid-build construction contract, Sergent Construction (SC) acted as general contractor as well as self-performed the following trades: demolition, carpentry, structural repairs, insulation, roof repairs, drywall, paint, and shutter replacement. Additional self-performed work included siding replacement, sealing of doors and windows, flashing repairs, wood siding, overhead doors, gutters, door repairs, and fencing. In total, SCS self-performed 90% of this project’s scope of work.
Facilities Maintenance, Repair, & Modernization
Grand Isle, Louisiana
Client: United States Coast Guard
Project Size: $0M – $2M
This design-build contract’s scope of work involved repairing additional storm damage at the Grand USCG Station caused by Hurricane Isaac. Damage to the site included water damage from roof leaks and flooding as well as structural damage from hurricane force winds. The work completed for this project included the removal and replacement of all the ductwork in 16 occupied USCG personal apartments, the repair of the standing seam metal roofing system, and the removal and replacement of two structural columns. The removal and replacement of the ductwork within the 16 apartments required Sergent Construction personal to schedule the work around each apartment occupant’s daily schedule. Sergent Construction also remove and re-install existing roof as necessary to ensure a weather tight seal.
With regards to the structural columns, Sergent Construction had discovered damages to two structural columns and base plates. These two columns provided for a safe and stabilized use of a three story USCG housing unit. As a result of SC’s discovery, the USCG included a requirement for a design-build engineering effort for the replacement of these two columns. This additional effort called for the design, removal, and replacement of these two structural columns, base plates, and spread footing. The complete design and engineering for this effort was completed by SC’s in-house design team in conjunction with SC’s on-site supervisory staff who provided the necessary in-field data necessary to quickly complete the design. While the design was under consideration, the Sergent Construction team quickly developed an extensive temporary shoring system along the exterior of the housing units. This temporary shoring, column, base plate, and footing design allowed for the complete removal and replacement of the two rotten 10”x10” columns while still allowing for continued and occupied use of the facility.
On this design-build construction contract, Sergent Construction (SC) acted as general contractor as well as self-performed the following trades: HVAC work, structural member removal and replacement, installation and removal of temporary shoring for the protection of existing structures, and repair of the standing seam metal roof’s weather tight gasket system. In total, SCS self-performed 85% of this task order’s scope of work.
Facilities Maintenance, Repair, & Modernization
Moffett Field, CA
Client: US Air Force National Guard
Project Size: $2M – $5M
This construction project involved the complete interior and exterior renovations of five buildings and the re-roofing of 11 buildings. The scope of work related to the exterior renovations included: installation of an underground high-voltage electrical distribution system, installation of a new emergency back-up power generator, installation of new underground communications and data systems, construction of a new parking lot including earthwork, paving, exterior lighting, landscaping, and concrete curbs and gutters.
Interior renovations included: demolition, in some cases complete gutting of the buildings, structural modifications, new electrical distribution systems, lighting systems, mechanical systems including, plumbing, compressed air, and HVAC systems which incorporated chillers, boilers, air handling units, VAV’s and an EMCS control system. The new floor plan configurations required the installation of framing and gypsum board partitions, new frames/doors and hardware, and interior finishes.
On this design-build construction contract, Sergent Construction (SC) acted as general contractor as well as self-performed the following trades: HVAC work, interior and exterior mechanical and structural, electrical, earthwork, and plumbing. In total, SCS self-performed 85% of this task order’s scope of work.
Facilities Maintenance, Repair, & Modernization
Fayetteville, North Carolina
Client: Department of Veterans Affairs
Project Size: $0M – $2M
This project’s scope of work involved the removal and replacement of two 20,000 CFM indoor central station Air Handler Units (AHUs) and associated equipment, plumbing, and electrical work at the Fayetteville VA Medical Center’s D-Wing located in Building 1. Work on this project included the installation of two new 20,000 CFM AHU’s, VFDs for both the AHUs and exhaust fans, intake louvers, and supply and return ductwork for the air handler units. Also included was the installation of a high performance 3-coat epoxy floor coating in Building 1.
Work included the installation of an updated HVAC DDC to control system for the newly installed AHU’s, exhaust fans, and humidifiers. The new DDC control system was tied into the Fayetteville VA Medical Center’s integrated digital building management systems or Building Automation System (BAS) control system. In addition, new electrical feeders, circuit breakers, and panel boards for the upsized AHUs and Exhaust Fans were installed.
On this design-bid-build construction contract, Sergent Construction (SC) acted as general contractor as well as self-performed the following trades: demolition, HVAC, mechanical piping, temp AHU installation, temporary electrical, electrical, equipment rigging, carpentry, and concrete. In All, SC self-performed 81% of this project’s scope of work.
Facilities Maintenance, Repair, & Modernization
Mobile, AL
Client: United States Coast Guard Civil Engineering Unit, Miami, FL
Project Size: $2M – $5M
This design-bid-build project involved the renovation of an existing electrical shop, medical clinic space, and office space in Building 101 at the USCG Station, Mobile, AL. This included the demolition of the buildings existing architectural finishes and associated building systems as well as asbestos abatement. New work included architectural finishes and caseworks, new electrical and lighting systems, and a new fire alarm system.
A new heating, ventilation, and air conditioning (HVAC) system was also installed including ductwork and refrigerant lines. Plumbing, plumbing fixtures, drywall, paint, and metal stud framing was included
Since the entire building was occupied during construction, Sergent Construction Services’ personnel provided temporary barriers, negative ventilation, and a closely coordinated schedule to work around the customers operational schedule.
On this design-bid-build construction contract, Sergent Construction Services acted as general contractor as well as self-performed the following trades: installation of plumbing, plumbing fixtures, installation of new HVAC system, installation of DDC Controls, FA system modifications, structural framing, and the installation of electrical systems and lighting. In all, SCS self-performed 75% of this project’s scope of work.